Reporting
to the delegation, Deputy Director of Department of Transport - Tran
Thien Truc said that component 7 has disbursed 198.698/309 billion VND,
reaching over 64% of the allocated capital. The sector is completing
advancing procedures for contractors. It is expected that by the end of
this month, disbursement will reach 74% and by December 31, 2023,
disbursement will reach 100% of the plan. For component 8, 827.4/995
billion VND has been disbursed, reaching 83.16% of the allocated
capital.
Director
of Department of Transport - Dang Hoang Tuan informs Secretary of
Provincial Party Committee, Chairman of Provincial People's Council on
the progress of Ho Chi Minh City Ring Road 3 project.
Up
to now, contractors in 3 construction packages have completed input
procedures and drawing design documents for main items in each phase;
mobilized human resources, built camps, operating houses and field
experiment stations, excavated public service road molds and prepared
ground for pile construction.
Currently,
construction package 2 has drilled 2/36 test piles, construction
package 3 has drilled 2/16 test piles and construction package 1 has dug
public service road molds reaching over 60%. According to the
assessment, the project basically completed the plan and progress
milestones required by the Government. However, there are still
difficulties due to sand supply.
Currently, units are gathering vehicles and machinery to construct the Ring Road 3 project of Ho Chi Minh City
As
for the Provincial Road 830E project, currently the unit are
constructing 4 packages in 2 sections including the section from the
intersection of Provincial Road 830 to Nguyen Van Nham street and the
section from Nguyen Van Nham to National Highway 1. However, the
progress is still slow. The main problems are related to site clearance,
making it impossible for units to carry out mass construction.
Secretary
of Provincial Party Committee, Chairman of Provincial People's Council -
Nguyen Van Duoc and the delegation directly inspect the Ring Road 3
project of Ho Chi Minh City
As
for site clearance work, for the key project of Ring Road 3 project of
Ho Chi Minh City, Ben Luc District People's Committee has paid 389/398
households, reaching 97.7%, total compensation amount is 837.6/857.226
billion VND, reaching 97.7%; The compensation area is 42.3/43.55
hectares, reaching 97.1%. To date, the People's Committees of communes
have considered preliminary resettlement policies for 127 cases whose
houses and residential land were affected. Of these, 110 cases are
eligible for resettlement with land and 17 cases are supported with
monetary resettlement.
Inspection delegation at Provincial Road 830E project
As
for the Provincial Road 830E project passing through Ben Luc district,
up to now, 717 households have been paid with an amount of over 1,242
billion VND, with an area of 32.9 hectares, reaching 81.6% of the
households and 82.8% of the area. There are currently 161 households/6.8
hectares that have not yet agreed with the compensation price. As for
the section through Can Duoc district, the Provincial People's Committee
agreed on the policy of temporarily not clearing the site from Rach
Chanh bridge to Provincial Road 830 (the section passing through the
expanded Phuc Long Industrial Park).
Secretary
of Provincial Party Committee, Chairman of Provincial People's Council -
Nguyen Van Duoc requests the Department of Transport, Provincial
People's Committee, Ben Luc District People's Committee, relevant
departments, branches and construction units to focus on overcoming
difficulties and speeding up progress of key projects to meet committed
schedule
At the meeting,
representatives of the Provincial People's Committee, Department of
Transport, relevant departments, branches and contractors discussed and
resolved difficulties and obstacles to speed up the project progress.
Speaking
at the meeting, Secretary of Provincial Party Committee, Chairman of
Provincial People's Council - Nguyen Van Duoc acknowledged the joint
efforts of Provincial People's Committee, Department of Transport, Ben
Luc District People's Committee, related sectors andconstruction
contractors, with the highest determination in implementing 2 key
projects of Ring Road 3 of Ho Chi Minh City and Provincial Road 830E,
achieving progress as planned.
He also
affirmed that the two key projects, Ho Chi Minh City Ring Road 3 and
Provincial Road 830E, are both very important in the socio-economic
development of the province as well as in regional connectivity.
Secretary
of Provincial Party Committee and Chairman of Provincial People's
Council - Nguyen Van Duoc affirms that the two key projects have very
important significance in the socio-economic development of the
province.
From the actual survey
and direct work with units, Secretary of Provincial Party Committee,
Chairman of Provincial People's Council - Nguyen Van Duoc also
recommended that the Provincial People's Committee continue to direct
relevant departments and branches to ensure implementation progress of 2
key projects and be responsible to the Provincial Party Standing
Committee. Departments and branches need to advise Provincial People's
Committee in maximizing the exploitation of existing land funds to
promptly allocate capital to implement 2 key projects on the basis of
ensuring the provisions of law, etc.
The
Department of Transport needs to have solution to remove difficulties
and obstacles for construction units, especially the supply of sand. In
case of exceeding the authority, it is necessary to promptly report to
the Provincial People's Committee for direction to remove difficulties
and obstacles.
Particularly for
construction contractors in the two projects, he suggested that it is
necessary to focus on mobilizing human and material resources,
organizing the implementation of many construction steps, overcoming
difficulties, promptly reporting and resolving difficulties and
obstacles ensure the progress.
Previously,
Secretary of Provincial Party Committee, Chairman of Provincial
People's Council - Nguyen Van Duoc and the delegation directly surveyed
construction packages under Component 7of Ring Road 3 project of Ho Chi
Minh City and Provincial Road 830E./.